基于日前风功率预测的风电消纳能力评估方法Evaluation on Capability of Wind Power Accommodation Based on Its Day-ahead Forecasting
贾文昭;康重庆;李丹;陈之栩;刘军;
摘要(Abstract):
准确掌握电力系统消纳风电的能力,有助于风电场建设规划,更可辅助实际运行的调度决策。风电消纳能力的评估应分析全时段、计及多因素、考虑日前风电出力预测、探寻风电"可消纳包络带"。提出了一种基于日前风功率预测的风电消纳能力评估方法,首先以日前预测所得风电为基本信息,优化常规机组的启停状态;然后基于此决策,探寻系统次日全时段可消纳风电的上下限,并基于二次规划模型生成极端风电出力作为判据样本,分析系统次日消纳风电的能力,进而为运行人员提供决策辅助。
关键词(KeyWords): 风电消纳能力;日前风电预测;全时段;极端风电出力;二次规划
基金项目(Foundation): 国家863高技术基金项目(2011AA05A101)~~
作者(Author): 贾文昭;康重庆;李丹;陈之栩;刘军;
Email:
DOI: 10.13335/j.1000-3673.pst.2012.08.042
参考文献(References):
- [1]Andrew M,Ryan W,Kevin P.The cost of transmission for windenergy:a review of transmission planning studies[EB/OL].2009-06-15.http://eetd.lbl.gov/EA/EMP.
- [2]Joseph F D.The economics and environmental impacts of large-scalewind power in carbon constrained world[D].Pittsburgh,USA:Carnegie Mellon University,2004.
- [3]Soren K,Poul-Erik M,Shimon A.The economics of wind peneration[EB/OL].2009-03-27.http://www.ewea.org/filedmin/ewea_documents/documents/POLICY_document/Economic of Wind EnergyMarch.
- [4]李俊峰,施鹏飞,高虎.中国风电发展报告[R].海口:海南出版社,2010:1-30.
- [5]国家电网公司.国家电网公司促进风电发展白皮书[R].北京:国家电网公司,2011.
- [6]崔杨,穆钢,刘玉.风电功率波动的时空分布特性[J].电网技术,2011,35(2):110-117.Cui Yang,Mu Gang,Liu Yu.Spatiotemporal distributioncharacteristic of wind power fluctuation[J].Power SystemTechnology,2011,35(2):110-117(in Chinese).
- [7]Rajesh K,Hu P,Roy B.A simplified wind power generation modelfor reliability evaluation[J].IEEE Trans on Energy Conversion,2006,21(2):533-540.
- [8]徐乾耀,康重庆,张宁,等.海上风电出力特性及其消纳问题探讨[J].电力系统自动化,2011,35(22):54-59.Xu Qianyao,Kang Chongqing,Zhang Ning,et al.A discussion onoffshore wind power output characteristics and its accommodation[J].Automation of Electric Power Systems,2011,35(22):54-59(inChinese).
- [9]Ronan D,Mark O.A new approach to quantify reserve demand insystems with significant installed wind capacity[J].IEEE Trans onPower Systems,2005,20(2):587-595.
- [10]汤宏,吴俊玲,周双喜.包含风电场电力系统的小干扰稳定分析建模和仿真[J].电网技术,2004,28(1):38-45.Tang Hong,Wu Junlin,Zhou Shuangxi.Modeling and simulation forsmall signal analysis of power system containing wind farm[J].PowerSystem Technology,2004,28(1):38-45(in Chinese).
- [11]张宁,周天睿,段长刚,等.大规模风电场接入对电力系统调峰的影响[J].电网技术,2010,34(1):152-158.Zhang Ning,Zhou Tianrui,Duan Changgang,et al.Impact oflarge-scale wind farm connecting with power grid on peak loadregulation demand[J].Power System Technology,2010,34(1):152-158(in Chinese).
- [12]Joseph F D.The economics and environmental impacts of large-scalewind power in carbon constrained world[D].Pittsburgh,USA:Carnegie Mellon University,2004.
- [13]侯佑华,房大中,齐军.大规模风电入网的有功功率波动特性分析及发电计划仿真[J].电网技术,2010,34(5):60-68.Hou Youhua,Fang Dazhong,Qi Jun.Analysis on active powerfluctuation characteristics of large-scale grid-connected wind farmand generation scheduling simulation under different capacity powerinjected from wind farms into power grid[J].Power SystemTechnology,2010,34(5):60-68(in Chinese).
- [14]Billnton R,Gao Y,Karki R.Composite system adequacy assessmentincorporating large-scale wind energy conversion systems consideringwind speed correlation[J].IEEE Trans on Power Systems,2009,25(1):106-116.
- [15]Dokopoulos P S,Patralexis A X,Manousaridis L M.Improvement ofpower quality distribution in a grid caused by wind turbines[C]//The8th International Conference on Harmonics and Quality ofPower.Athens,Greece:IEEE,1998:917-922.
- [16]孙元章,吴俊,李国杰.风力发电对电力系统的影响[J].电网技术,2007,31(20):55-62.Sun Yuanzhang,Wu Jun,Li Guojie.Influence research of wind powergeneration on power systems[J].Power System Technology,2007,31(20):55-62(in Chinese).
- [17]孙荣富,张涛,梁吉.电网接纳风电能力的评估及应用[J].电力系统自动化,2011,35(4):70-76.Sun Rongfu,Zhang Tao,Liang Ji.Evaluation and application of windpower integration capacity in power grid[J].Automation of ElectricPower Systems,2011,35(4):70-76(in Chinese).
- [18]王芝茗,苏安龙,鲁顺.基于电力平衡的辽宁电网接纳风电能力分析[J].电力系统自动化,2010,24(3):86-90.Wang Zhiming,Su Anlong,Lu Shun.Analysis on capacity of windpower integrated into liaoning power grid based on power balance[J].Automation of Electric Power Systems,2010,24(3):86-90(inChinese).
- [19]衣立东,朱敏亦,魏磊.风电并网后西北电网调峰能力的计算方法[J].电网技术,2010,34(2):129-132.Yi Lidong,Zhu Minyi,Wei Lei.A computing method for peak loadregulation ability of northwest China power grid connected withlarge-scale wind farms[J].Power System Technology,2010,34(2):129-132(in Chinese).
- [20]国家能源局.风电厂功率预测预报管理暂行办法[S].北京市:国家能源局,2011.