摘要(Abstract):
在机会约束规划的框架下,研究了在兼顾系统运行的可靠性和经济性时,如何考虑发电机组的故障停运和负荷预测误差等不确定性因素,以便确定系统所需的最优旋转备用容量。在以最小化旋转备用的购买成本为目标、以系统的安全性要求为机会约束的条件下,构造了确定系统所需的最优旋转备用容量的数学模型,并采用基于蒙特卡洛仿真的遗传算法进行求解。最后以包含18台机组的电力系统为例对所提出的模型与方法进行了说明。
关键词(KeyWords): 电力市场;旋转备用;机会约束规划;遗传算法;蒙特卡洛仿真
基金项目(Foundation): 国家重点基础研究发展计划项目(973项目)(2004CB217905);; 教育部“新世纪优秀人才支持计划”资助项目(NCET-04-0818);; 香港政府研究资助局(RGC)资助项目(5215/03E)~~
作者(Author): 王乐;余志伟;文福拴;
Email:
DOI:
参考文献(References):
- [1]Wang J X,Wang X F,Wu Y.Operating reserve model in power market[J].IEEE Trans on Power Systems,2005,20(1):223-229.
- [2]Tseng C L,Oren S S,Svoboda A,et al.Price-based adaptive spinning reserve requirements in power system scheduling[J].International Journal of Electrical Power and Energy Systems,1999,21(2):137-145.
- [3]Yu C W,Zhao X S,Wen F S,et al.Pricing and procurement of operating reserves in competitive pool-based electricity markets[J].Journal of Electric Power Systems Research,2005,73(1):37-43.
- [4]张国全,王秀丽,王锡凡.电力市场中旋转备用的效益和成本分析[J].电力系统自动化,2000,24(21):14-18.Zhang Guoquan,Wang Xiuli,Wang Xifan.Study on benefits and costs of spinning reserve capacity in power market[J].Automation of Electric Power Systems,2000,24(21):14-18(in Chinese).
- [5]Chan C Y,Chan T K,Ni Y X,et al.A decentralized approach for operating reserve procurement[C].Proceeding of6th International Conference on APSCOM,Hong Kong,2003.
- [6]孟祥星,韩学山.不确定性因素引起备用的探讨[J].电网技术,2005,29(1):30-34.Meng Xiangxing,Han Xueshan.Discussion on reserve caused by uncertainty factors[J].Power System Technology,2005,29(1):30-34(in Chinese).
- [7]何永秀,黄文杰,谭忠富,等.电力备用市场化运营需求研究[J].中国电机工程学报,2004,24(3):46-50.He Yongxiu,Huang Wenjie,Tan Zhongfu,et al.A study on demand of electricity reserve market in marketing operation[J].Proceedings of the CSEE,2004,24(3):46-50(in Chinese).
- [8]杨梓俊,丁明,孙昕.电力市场下综合考虑系统可靠性和旋转备用效益的机组组合[J].电网技术,2003,27(6):13-18.Yang Zijun,Ding Ming,Sun Xin.Unit commitment problem under the condition of electricity market considering system reliability and benefit from spinning reserve[J].Power System Technology,2003,27(6):13-18(in Chinese).
- [9]谭伦农,张保会,市场环境下的事故备用容量[J].中国电机工程学报,2004,22(11):54-58.Tan Lunnong,Zhang Baohui.Reserve capacity for accident in power market environment[J].Proceedings of the CSEE,2004,22(11):54-58(in Chinese).
- [10]焦连伟,文福拴,祁达才,等.电力市场中辅助服务的获取与定价[J].电网技术,2002,26(7):1-6.Jiao Lianwei,Wen Fushuan,Qi Dacai,et al.Procurement and pricing of ancillary services in electricity markets[J].Power System Technology,2002,26(7):1-6(in Chinese).
- [11]Oren S S.Design of ancillary service markets[C].Proceedings of the34th IEEE Hawaii International Conference on System Sciences,Hawaii,2001.
- [12]Liu Y,Alaywan Z,Liu S,et al.A rational buyer's algorithm used for ancillary service procurement[C].IEEE Power Engineering Society Winter Meeting,Singapore,2000.
- [13]刘宝碇,赵瑞清.随机规划与模糊规划[M].北京:清华大学出版社,1998.
- [14]杨宁,文福拴.基于机会约束规划的输电系统规划方法[J].电力系统自动化,2004,28(14):23-27.Yang Ning,Wen Fushaun.Transmission system expansion planning based on chance constrained programming[J].Automation of Electric Power Systems,2004,28(14):23-27(in Chinese).
- [15]马新顺,文福拴,刘建新.构造发电公司最优报价策略的机会约束规划方法[J].电网技术,2005,29(10):35-39.Ma Xinshun,Wen Fushuan,Liu Jianxin.A chance constrained programming based approach for building optimal bidding strategies for generation companies with risk management[J].Power System Technology,2005,29(10):35-39(in Chinese).