电力电量平衡评价指标体系及其综合评估方法研究Research on Evaluation Index System and Synthetical Evaluation Method for Balance of Electric Power and Energy
蒲天骄;陈乃仕;葛贤军;王伟;刘广一;
摘要(Abstract):
基于关键业绩指标分析法构建了以充裕性、供电有序性、节能环保性、经济性为关键指标的电力电量平衡评价指标体系。采用主客观结合的层次分析?熵权组合法作为评价指标权重的计算方法,基于逼近理想点排序法对电力电量平衡方案进行综合评估。通过对实际算例进行分析,验证了该评估体系和综合评估方法的有效性和正确性。
关键词(KeyWords): 电力电量平衡;层次分析-熵权组合法;逼近理想点法;关键业绩指标分析法
基金项目(Foundation): 国家电网公司科技项目“基于能源资源配置特点的短期电力电量平衡模型的研究与应用”
作者(Author): 蒲天骄;陈乃仕;葛贤军;王伟;刘广一;
Email:
DOI: 10.13335/j.1000-3673.pst.2015.01.038
参考文献(References):
- [1]吴东平,万永华.日电力电量平衡的余荷逐次后移法[J].水力发电学报,1994,46(3):31-35.Wu Dongping,Wan Yonghua.The remaining load sucessive backward method about daily electric power and energy balance[J].Journal of Hydroelectric Engineering,1994,46(3):31-35(in Chinese).
- [2]庞峰.电力电量平衡新方法[J].水力发电学报,2001,4(6):116-121.Pang Feng.The new method about electric power and energy balance[J].Journal of Hydroelectric Engineering,2001,4(6):116-121(in Chinese).
- [3]陈森林.电力电量平衡算法及其应用研究[J].水力发电,2004,30(2):15-19.Chen Senlin.Study and application of the algorithm of the electric power and energy balance method[J].Water Power,2004,30(2):15-19(in Chinese).
- [4]朱泽磊,周京阳,潘毅,等.考虑电力电量平衡的安全约束经济调度[J].中国电机工程学报,2013,33(10):168-176.Zhu Zelei,Zhou Jingyang,Pan Yi,et al.Security constrained economic dispatch considering balance of electric power and energy[J].Proceedings of the CSEE,2013,33(10):168-176(in Chinese).
- [5]王芝茗,苏安龙,鲁顺.基于电力平衡的辽宁电网接纳风电能力分析[J].电力系统自动化,2010,34(3):86-91.Wang Zhiming,Su Anlong,Lu Shun.Analysis on capacity of wind power integrated into Liaoning power grid based on power balance[J].Automation of Electric Power Systems,2010,34(3):86-91(in Chinese).
- [6]徐玮,康重庆,揣小勇,等.基于不确定型电力电量平衡的电网企业购电成本分析[J].电网技术,2006,30(21):15-20.Xu Wei,Kang Chongqing,Chuai Xiaoyong,et al.Electricity purchasing cost calculation based on uncertain analysis of power supply-demand balancing for power grid corporation[J].Power System Technology,2006,30(21):15-20(in Chinese).
- [7]Wu T Y,Shieh S S,Jang S S,eta1.Optimal energy management integration for a petrochemical plant under-considerations of uncertain power supplies[J].IEEE Transactions on Power Systems,2005,20(31):1431-1439.
- [8]李伟刚,张加力,潘毅,等.“三公”调度模式下福建省中长期电力电量平衡研究[C]//2012电气与信息国际会议(Part V).湖南,长沙:湖南大学电气与信息工程学院,2012,879-883.
- [9]Ishikida V P P.Pricing of electric power under uncertainty:information and efficiency[J].IEEE Transactions on Power Systems,1995,10(2):884-890.
- [10]张健,蒲天骄,王伟,等.智能电网示范工程综合评价指标体系[J].电网技术,2011,35(6):5-9.Zhang Jian,Pu Tianjiao,Wang Wei,et al.A comprehensive assessment index system for smart grid demonstration projects[J].Power System Technology,2011,35(6):5-9(in Chinese).
- [11]王彬,何光宇,梅生伟,等.智能电网评估指标体系的构建方法[J].电力系统自动化,2011,35(23):1-5.Wang Bin,He Guangyu,Mei Shengwei,et al.Construction method of smart grid’s assessment index system[J].Automation of Electric Power Systems,2011,35(23):1-5(in Chinese).
- [12]倪娜,申静.电网企业关键业绩指标体系探讨[J].陕西电力,2010,2(7):65-70.Ni Na,Shen Jing.Probe into key achievement index system in power network enterprise[J].Shanxi Electric Power,2010,2(7):65-70(in Chinese).
- [13]赵云飞,陈金富.层次分析法在及其在电力系统中的应用[J].电力自动化设备,2004,24(9):85-87.Zhao Yunfei,Chen Jinfu.Analytic hierarchy process and its application in power system[J].Electric Power Automation Equipment,2004,24(9):85-87(in Chinese).
- [14]Satty T L.The analytic hierarchy process[M]:New York,USA:Me Graw-Hill Inc,1980;13-47.
- [15]Bertolini M,Braglia M,Carmignani G.Application of the AHP Methodology in making a proposal for a public work contract[J].International Journal of Project Management,2006,24(5):422-430.
- [16]王钦,文福拴,刘敏,等.基于模糊集理论和层次分析法的电力市场综合评价[J].电力系统自动化,2009,33(7):32-37.Wang Qin,Wen Fushuan,Liu Min,et al.Combined use of fuzzy set theory and analytic hierarchy process for coprehensive assessment of electricity markets[J].Automation of Electric Power Systems,2009,33(7):32-37(in Chinese).
- [17]李军,李继光,姚建刚,等.属性识别和G1-熵权法在电能质量评价中的应用[J].电网技术,2009,33(14):56-61.Li Jun,Li Jiguang,Yao Jiangang,et al.Application of attribute recognition and G1-Entropy method in evaluation of power quality[J].Power System Technology,2009,33(14):56-61(in Chinese).
- [18]虞晓芬,傅玳.多指标综合评价方法综述[J].统计与决策,2004(11):119-121.Yu Xiaofen,Fu Dai.Survey on the multi-index comprehensive evaluation method[J].Statistics and Decision,2004(11):119-121(in Chinese).
- [19]胡元潮,阮羚,阮江军,等.基于改进逼近理想点法的变电站智能化改造评估[J].电网技术,2012,36(10):42-48.Hu Yuanchao,Ruan Ling,Ruan Jiangjun,et al.Evaluation on intelligent renovation of substations based on improved TOPSIS[J].Power System Technology,2012,36(10):42-48(in Chinese).
- [20]刘艳锋.利用肯德尔和谐系数检验测量结果的可信度[J].新乡教育学院学报,2006,19(2):95-96.Liu Yanfeng.Practical application of Kender’s harmonious coefficient in faithfulness in measurement and test results[J].Journal of Xinxiang Education College,2006,19(2):95-96(in Chinese).
- [21]孙强,葛旭波,刘林,等.智能电网多属性网络层次组合评价法及其应用研究[J].电网技术,2012,36(10):49-54.Sun Qiang,Ge Xubo,Liu Lin,et al.Multi-attribute network process comprehensive evaluation method for smart grid and its application[J].Power System Technology,2012,36(10):49-54(in Chinese).
- [22]孙涛.基于熵值法和改进的理想点法的建设项目多目标综合优化[D].重庆:重庆大学,2010.