直驱永磁同步风电机组高电压穿越技术研究与试验Research and Experiment on High Voltage Ride Through for Direct-Drive PMSG-Based Wind Turbines
代林旺;秦世耀;王瑞明;李少林;陈晨;
摘要(Abstract):
针对大容量直驱永磁同步风电机组的高电压穿越问题,研究了电网电压升高对全功率变流器母线电压的影响;在风电机组不同的无功输出情况下,分析了机组升压变压器阻抗对并网点电压影响规律。在此基础上,确定了电网高电压故障下无功电流注入的原则,提出了基于变流器动态无功控制的高电压穿越控制策略,并从"高电压判断-高穿执行-高穿结束"3个方面分析了主控系统协调配合机制。在MATLAB中建立了2.5 MW直驱永磁风电机组的仿真模型,实现了风电机组高电压穿越全过程动态仿真;利用电网高电压发生装置,在MW级直驱永磁同步风电机组上进行了高电压穿越现场试验研究,试验结果表明理论与仿真分析的准确性及控制策略的有效性。
关键词(KeyWords): 直驱永磁同步风电机组;高电压穿越;动态无功控制;现场试验
基金项目(Foundation): 国家科技支撑计划项目(2015BAA07B01)~~
作者(Author): 代林旺;秦世耀;王瑞明;李少林;陈晨;
Email:
DOI: 10.13335/j.1000-3673.pst.2017.2077
参考文献(References):
- [1]Conroy J F,Watson R.Low voltage ride-through of a full converter wind turbine with permanent magnet generator[J].IET Renewable Power Generation,2007,1(3):182-189.
- [2]Hansen A D,Michalke G.Multi-pole permanent magnet synchronous generator wind turbines,grid support capability in uninterrupted operation during grid faults[J].IET Renewable Power Generation,2009,3(3):333-348.
- [3]李建林,徐少华.直接驱动型风力发电系统低电压穿越控制策略[J].电力自动化设备,2012,32(1):29-33.Li Jianlin,Xu Shaohua.Control strategy of low voltage ride-through for direct-drive wind power generation system[J].Electric Power Automation Equipment,2012,32(1):29-33(in Chinese).
- [4]李和明,董淑惠,王毅,等.永磁直驱风电机组低电压穿越时的有功和无功协调控制[J].电工技术学报,2013,28(5):73-81.Li Heming,Dong Shuihui,Wang Yi,et al.Coordinated control of active and reactive power of PMSG-Based wind turbines for low voltage ride through[J].Transactions of China Electroterchnical Society,2013,28(5):73-81(in Chinese).
- [5]陈浩,胡晓波,严干贵,等.直驱永磁风力发电机组低电压穿越的协调控制策略[J].电网技术,2015,37(5):1464-1470.Chen Hao,Hu Xiaobo,Yan Gangui,et al.A coordinated control strategy for low voltage ride-though of direct-drive permanent magnet wind power generating units[J].Power System Technology,2015,37(5):1464-1470(in Chinese).
- [6]孟永庆,王健,李磊,等.考虑风机转速限制及卸荷电路优化的永磁同步电机新型低电压穿越协调控制策略[J].中国电机工程学报,2015,35(24):6283-6292.Meng Yongqing,Wang Jian,Li Lei,et al.New low voltage ride-through coordinated control schemes of permanent magnet synchronous generator considering rotor speed limit and DCdischarging circuit optimization[J].Proceedings of the CSEE,2015,35(24):6283-6292(in Chinese).
- [7]Haitham M Y,Hanafy H H,Mohab M H.Enhancement low-voltage ride through capability of permanent magnet synchronous generatorbased wind turbines using interval type-2 fuzzy control[J].IETRenewable Power Generation,2016,10(3):339-348.
- [8]李少林,王伟胜,王瑞明,等.双馈风电机组高电压穿越控制策略与试验研究[J].电力系统自动化,2016,40(16):76-82.Li Shaolin,Wang Weisheng,Wang Ruiming,et al.Control strategy and experiment research on high voltage ride through for DFIG-based wind turbines[J].Automation of Electric Power Systems,2016,40(16):76-82(in Chinese).
- [9]李明节.大规模特高压交直流混联电网特性分析与运行控制[J].电网技术,2016,40(4):985-991.Li Mingjie.Characteristic analysis and operational control of large-scale hybrid UHV AV/DC power grid[J].Power System Technology,2016,40(4):985-991(in Chinese).
- [10]李勇.强直弱交区域互联大电网运行控制技术与分析[J].电网技术,2016,40(12):3756-3760.Li Yong.Technology and practice of the operation control of large power grid connected with weak AC area[J].Power System Technology,2016,40(12):3756-3760(in Chinese).
- [11]刘雪菁,朱丹,宋飞,等.风电机组高电压穿越技术研究[J].可再生能源,2013,31(11):34-38.Liu Xuejing.Zhu Dan,Song Fei,et al.Feasibility analysis on high voltage ride-through of wind turbines[J].Renewable Energy Resources,2013,31(11):34-38(in Chinese).
- [12]马伟娜.直驱型风力发电机组高电压穿越技术研究与应用[D].北京:华北电力大学,2015.
- [13]边晓燕,田春笋,符杨.提升直驱型永磁风电机组故障穿越能力的改进控制策略研究[J].电力系统保护与控制,2016,44(9):69-74.Bian Xiaoyan,Tian Chunsun,Fu Yang.A coordinated control strategy for fault ride-though capacity of direct-drive permanent magnet wind power generating units[J].Power System Protection and Control,2016,44(9):69-74(in Chinese).
- [14]陈瑶.直驱型风力发电系统全功率并网变流技术的研究[D].北京:北京交通大学,2008.
- [15]Mohseni M,Islam S M.Transient control of DFIG-based wind power plants in compliance with the Australian grid code[J].IEEETransactions on Power Electronics,2012,27(6):2813-2824.
- [16]Kalverkamp F,Brelie S V D,Nguyen T D,et al.Comparative analysis of European Grid Codes and compliance standards for distributed power generation plants with respect to future requirements of ENTSO-E and CENELEC[C]//International ETG Congress.Bonn,Germany:IEEE,2015:605-610.