大规模风电场的发电充裕度与容量可信度评估Assessment on Generation Adequacy and Capacity Credit for Large-Scale Wind Farm
汪海瑛;白晓民;
摘要(Abstract):
风力发电异于常规电源的运行特性,这使得关于它的系统发电充裕度评估技术与传统方法有所不同。在通用风速模型基础之上,综合考虑风机的输出功率特性以及风向的统计分布特性,建立了风电场的发电可靠性评估模型;同时还考虑了多种尾流情况的影响,建立了尾流效应模型;并采用解析技术,在IEEE的可靠性测试系统中对不同实验方案下含风电场的系统总体发电充裕度和风电场的容量可信度进行评估。评估结果验证了混合考虑不同情况尾流对发电充裕度的影响程度,以及在计算时选取的风电场容量模型状态数对结果准确性的影响程度和它与系统风电穿透率水平之间的关系;还验证了风况、风场布局和风电穿透率水平等因素对等风电场的容量可信度的影响程度。
关键词(KeyWords): 风力发电;发电充裕度;可靠性;尾流效应;容量可信度
基金项目(Foundation):
作者(Author): 汪海瑛;白晓民;
Email:
DOI: 10.13335/j.1000-3673.pst.2012.06.036
参考文献(References):
- [1]戴慧珠,王伟胜,迟永宁.风电场接入电力系统研究的新进展[J].电网技术,2007,31(20):16-23.Dai Huizhu,Wang Weisheng,Chi Yongning.Recent wind powerintegration study in China[J].Power System Technology,2007,31(20):16-23(in English).
- [2]张丽英,叶廷路,辛耀中,等.大规模风电接入电网的相关问题及措施[J].中国电机工程学报,2010,30(25):1-9.Zhang Liying,Ye Tinglu,Xin Yaozhong,et al.Problems and measuresof power grid accommodating large scale wind power[J].Proceedingsof the CSEE,2010,30(25):1-9(in Chinese).
- [3]陈树勇,戴慧珠,白晓民,等.风电场的发电可靠性模型及其应用[J].中国电机工程学报,2000,20(3):26-29.Chen Shuyong,Dai Huizhu,Bai Xiaomin,et al.Reliability model0f wind power plants and its application[J].Proceedings of the CSEE,2000,20(3):26-29(in Chinese).
- [4]栗文义,张保会,巴根.风能大规模利用对电力系统可靠性的影响[J].中国电机工程学报,2008,28(1):100-105.Li Wenyi,Zhang Baohui,Bagen.Reliability impacts of large scaleutilization of w ind energy on electric power systems[J].Proceedingsof the CSEE,2008,28(1):100-105(in Chinese).
- [5]徐玉琴,吴颖超.考虑风力发电影响的配电网可靠性评估[J].电网技术,2011,35(4):154-158.Xu Yuqin,Wu Yingchao.Reliability evaluation for distribution systemconnected with wind-turbine generators[J].Power SystemTechnology,2011,35(4):154-158(in Chinese).
- [6]Billinton R,Gao Y.Multistate wind energy conversion system modelsfor adequacy assessment of generating systems incorporating windenergy[J].IEEE Trans on Energy Conversion,2008,23(1):163-170.
- [7]Giorsetto P,Utsurogi K F.Development of a new procedure forreliability modeling of wind turbine generators[J].IEEE Trans onPower Apparatus and Systems,1983,102(1):134-143.
- [8]Karki R,Hu P,Billinton R.A simplified wind power generationmodel for reliability evaluation[J].IEEE Trans on EnergyConversion,2006,21(2):533-540.
- [9]Correia P F,Ferreira de Jesus J M.Simulation of correlated windspeed and power variates in wind parks[J].Electric Power SystemsResearch,2010,80(5):592-598.
- [10]张硕,李庚银,周明,等.风电场可靠性建模[J].电网技术,2009,33(13):37-41.Zhang Shuo,Li Gengyin,Zhou Ming,et al.Reliability modeling oflarge-scale wind farms[J].Power System Technology,2009,33(13):37-41(in Chinese).
- [11]刘威,赵渊,周家启,等.计及风电场的发输配电系统可靠性评估[J].电网技术,2008,32(13):69-74.Liu Wei,Zhao Yuan,Zhou Jiaqi,et al.Reliability Assessment ofpower generation transmission and distribution systems containingwind farms[J].Power System Technology,2008,32(13):69-74(inChinese).
- [12]Ali M,Matevosyan J,Milanovi J V,et al.Effect of wakeconsideration on estimated cost of wind energy curtailments[C]//8thInternational Workshop on Large-Scale Integration of Wind Powerinto Power Systems as well as on Transmission Networks for OffshoreWind Farms.Bremen,Germany:Wind Integration Workshop,2009:20-25.
- [13]Jensen N O.A note on wind generator interaction[R].Roskilde:Ris National Laboratory,1983.
- [14]曹娜,赵海翔,任普春,等.风电场动态分析中风速模型的建立及应用[J].中国电机工程学报,2007,27(36):68-72.Cao Na,Zhao Haixiang,Ren Puchun,et al.Establish and applicationof wind speed model in wind farm dynamic analysis[J].Proceedingsof the CSEE,2007,27(36):68-72(in Chinese).
- [15]Ali M,Ilie I-S,Milanovi J V,et al.Probabilistic clustering of windgenerators[C]//IEEE Power and Energy Society GeneralMeeting.Minneapolis,USA:IEEE,2010:13-17.
- [16]王海超,鲁宗相,周双喜.风电场发电容量可信度研究[J].中国电机工程学报,2005,25(10):103-106.Wang Haichao,Lu Zongxiang,Zhou Shuangxi.Research on thecapacity credit of wind energy resources[J].Proceedings of theCSEE,2005,25(10):103-106(in Chinese).
- [17]Castro R M,Ferreira L A F.A comparison between chronological andprobabilistic methods to estimate wind power capacity credit[J].IEEETrans on Power System,2001,16(4):904-909.
- [18]A Report Prepared by the Reliability Test System Task Force of theApplication of Probability Methods Subcommittee.IEEE reliabilitytest system[J].IEEE Trans on Power Apparatus and Systems,1979,98(6):2047-2054.
- [19]赵伟然,徐青山,祁建华,等.风电场选址与风机优化排布实用技术探讨[J].电力科学与工程,2010,26(3):1-4.Zhao Weiran,Xu Qingshan,Qi Jianhua,et al.Discussion of windfarm sitting and wind turbine layout optimizing technology[J].Electric Power Science and Engineering,2010,26(3):1-4(inChinese).
- [20]Li Yifeng.Bulk system reliability evaluation in a deregulated powerindustry[D].Saskatoon:University of Saskatchewan,2003.